Docket Number PF06-11

Listed here in Ascending Date Order by Date Posted to FERC eLibrary.
NOTE: The Docket List on the FERC website is in Date Order by Date Filed, rather than by Date Posted.

Color Key: Project Developer, Contractors & Supporters
Project Opponents
Project Neutral
Unknown, non-public comments

2006 August


2006 August 2


Filed By: CHAIR AND IMMEDIATE STAFF (CHAIR)
Filed Date: 7/25/2006
Accession No: 20060802-0126
Description: Response to Senator Olympia J Snowe's 6/15/06 letter on behalf of her constitutent of Pembroke, Maine re the Quooday Bay Liquefied Natural Gas Import and Regasification Project under PF06-11.
Information: FILE LIST


Filed By: CHAIR AND IMMEDIATE STAFF (CHAIR)
Filed Date: 7/25/2006
Accession No: 20060802-0127
Description: Letter responding to Senator Olympia J Snowe's letter dated 7/15/06 on behalf of her constitutent of Pembroke, Maine re the Quooday Bay Liquefied Natural Gas Import and Regasification project under PF06-11.
Information: FILE LIST


2006 August 4


Filed By: ENVIRONMENTAL & ENGINEERING REVIEW [Kopka, Robert]
Filed Date: 8/4/2006
Accession No: 20060804-3002
Description: Letter to Quoddy Bay LLC enclosing their comments on its draft Resource Reports 1 through 3 that that its provided for the proposed Quoddy Bay LNG Project under PF06-11. [FERC lists a cornucopia of problematic questions for Quoddy Bay LLC to answer, again demonstrating that Quoddy Bay LLC doesn't have the required understanding or competence necessary to build or operate an LNG terminal.]
Information:FILE LIST


Filed By: MAINE DEPARTMENT OF MARINE RESOURCES
Filed Date: 4/27/2006 [There is no explanation as to why it took 3.5 months for this comment to be posted by FERC.]
Accession No: 20060804-0083
Description: Maine Department of Marine Resources requests to participate as a cooperating agency in the Quoddy Bay LNG proceeding under PF06-11.
Information: FILE LIST


2006 August 7


Filed By: ENVIRONMENTAL & ENGINEERING REVIEW [Kopka, Robert]
Filed Date: 8/7/2006
Accession No: 20060807-3030
Description: Letter to Quoddy Bay LLC enclosing FERC Staff's comments on its Draft Resource Reports 1 through 3 provided for the Quoddy Bay LNG Project under PF06-11.
Information: FILE LIST


2006 August 11


Filed By: QUODDY BAY LLC
Filed Date: 8/11/2006
Accession No: 20060811-3010
Description: Quoddy Bay, LLC submits its pre-filling monthly status report for the period ending 8/10/06 re Quoddy Bay LNG Import and Regasification Terminal Project under PF06-11.
Information:FILE LIST


Filed By: ENERGY PROJECTS, OFFICE OF [Kopka, Robert]
Filed Date: 8/11/2006
Accession No: 20060811-3010
Description: Letter to Quoddy Bay LLC enclosing FERC Staff's comments on Draft Resource Reports 11 and 13 for the planned Quoddy Bay LNG Import and Regasification Terminal Project under PF06-11.
Information:FILE LIST


Filed By: ENERGY PROJECTS, OFFICE OF [Kopka, Robert]
Filed Date: 8/11/2006
Accession No: 20060811-3011
Description: Letter to Quoddy Bay, LLC enclosing FERC comments on its Quoddy's draft Resource Reports 4 through 11 provided for the proposed Quoddy Bay LNG Project under PF06-11.
Information:FILE LIST

WEBMASTER'S COMMENTS: Quoted from the filing:

"Are there any other pertinent tribal groups or authorities that should be involved?"

An interesting question, since the Indian Township Passamaquoddy Reservation, as well as other Tribal members, have not given their permission to lease the Split Rock site to Quoddy Bay LLC. Also, the Bureau of Indian Affairs illegally relinquished its statutory Indian Trust responsibility to conduct archaeological studies of the site that FERC is referring to.

"In Section 5.2.1.1, indicate any economic losses associated with construction and operation impacts from the Import Terminal and the Sendout Pipeline on important commercial and recreational fish, shellfish, and other aquatic species in both marine and freshwater habitats."

Each LNG ship — by taking on millions of gallons ballast seawater and millions of gallons of seawater for engine cooling, would kill off significant numbers of lobster larvae — as well as other commercial species, damaging the lobster fishery in Maine, New Brunswick, and possibly in New Hampshire, Nova Scotia, and Massachusetts.

"In Section 5.2.1.5.2, clarify the discrepancy on page 5-6 about additional government expenditures for road maintenance during operation of the LNG Terminal. The first sentence of the first paragraph states that, “there may be need for limited additional government expenditures relating to the Project for road maintenance;” however, the second paragraph states that, “Quoddy Bay does not anticipate any additional Project-related road maintenance during the operation of the Project.”

The above is just another example of how Quoddy Bay LLC deals with truth, and mirrors how they have been dealing with the public. Following is yet another example:

"Section 5.2.1.10 states that no agricultural land, pasture, or timberland would be affected by construction of the LNG Terminal. During the July site visit, it appears that at least a portion of an existing blueberry field would be impacted by the LNG Storage Facility."

The FERC comments also require Quoddy Bay LLC to respond to issues regarding Environmental Justice; dredging of Half Moon Cove, and contamination that dredging might produce; the impact on educational and recreational uses of Split Rock; the effects of the facility on the proposed Split Rock boat landing; impacts on the shell fishery; plus a seemingly endless list of missing data, explanations, and justifications from Quoddy Bay LLC's records that have been submitted to FERC.


2006 August 16


Filed By: PERRY, TOWN OF (ME) [Turner, David; Adams, Richard; Guisinger, Jeanne]
Filed Date: 8/14/2006
Accession No: 20060816-0238
Description: Town of Perry, ME submits a petition to intervene regarding the pending license proceeding with Quoddy Bay LNG under PF016-11.
Information:FILE LIST


Filed By: FOREIGN AFFAIRS AND INTERNATIONAL TRADE CANADA [Fawcett, Peter]
Filed Date: 8/15/2006
Accession No: 20060816-0231
Description: Foreign Affairs & International Trade Canada expressses interest in the current US regulatory process surrounding the two liquefield natural gas projects currenlty under FERC review on the Maine coast of Passamaquoddy Bay, PF06-11.
Information: FILE LIST


2006 August 17


Filed By: PERRY, TOWN OF (ME) [Turner, David]
Filed Date: 8/17/2006
Accession No: 20060817-0205
Description: The Town of Perry, ME informs FERC et al that the Land Use and Development Permit Regulations et al have been deemed applicable to the Quoddy Bay LNG Project and should be included in Section 380.1 under PF06-11.
Information:FILE LIST


Filed By: PERRY, TOWN OF (ME) [Turner, David]
Filed Date: 8/17/2006
Accession No: 20060817-0206
Description: The Town of Perry, ME informs FERC et al that the Land Use and Development Permit Regulations et al have been deemed applicable to the Quoddy Bay LNG Project and should be included in Section 380.1 etc under PF06-11. [This appears to be a duplicate to Accession No: 20060817-205.]
Information:FILE LIST


Filed By: ENERGY PROJECTS, OFFICE OF [Ruhkamp, Todd]
Filed Date: 8/17/2006
Accession No: 20060817-3018
Description: Letter informing Mr. & Mrs. Merrill C. Morriss, Jr. that their motion to intervene in PF06-11 is premature given the pre-filing nature of this proceeding etc.
Information:FILE LIST


Filed By: ENERGY PROJECTS, OFFICE OF [Ruhkamp, Todd]
Filed Date: 8/17/2006
Accession No: 20060817-3019
Description: Letter informing the Town of Perry, Maine of its Premature Motion to Intervene re Quoddy Bay, LLC under PF06-11.
Information: FILE LIST


2006 August 18


Filed By: INDIVIDUAL [Cheverie, Donald]
Filed Date: 8/18/2006
Accession No: 20060818-5029
Description: Comments of Individual under PF06-11. Re: Resource Reports, maps and list [This Pembroke landowner requests maps showing the proposed pipeline route, and showing the civilian assets along the LNG ship transit route.]
Information: FILE LIST


2006 August 24


Filed By: ENVIRONMENTAL & ENGINEERING REVIEW [Hoffmann, Richard]
Filed Date: 8/24/2006
Accession No: 20060824-3024
Description: Letter requesting Quoddy Bay LLC to file within 60 days, a complete set of the revised draft Resource Reports that address the comments in FERC's previous letters dated August 4 and 11 August 13, 2006 under PF06-11. WEBMASTER'S COMMENTS: Quoddy Bay LLC once again demonstrates their incompetence by failing to meet FERC's draft Resource Reports deadline requirement. This pushes back — by 60 days — the date that they can file a formal application. They now can't file any sooner than the end of October, but a more realistic time would be November, December, or later. They're even farther behind in the race they've already lost.
Information:FILE LIST


Filed By: INDIVIDUAL [Mann, Hal & Amy]
INDIVIDUAL
Filed Date: 8/24/2006
Accession No: 20060824-5008
Description: Comments of Hal and Amy Mann in opposition to the LNG development in Maine under PF06-11, et al.
Information: FILE LIST


Top

Add our banner to your webpage: Save Passamaquoddy Bay

Read about the effort to Fix FERC: FixFERC



@MEMBER OF PROJECT HONEY POT
Spam Harvester Protection Network
provided by Unspam