2014 November

Docket Number PF14-19

Listed here in Ascending Date Order by Date Posted to FERC eLibrary.
NOTE: The Docket List on the FERC website is in Date Order by Date Filed, rather than by Date Posted.

Color Key: Project Developer, Contractors & Supporters
Project Opponents
Project Neutral
Unknown, non-public comments

Pre-filing
2014 November

Listed here in Ascending Date Order by Posted Date, rather than by Filed Date to FERC eLibrary.
NOTE: The Docket List on the FERC website is in Date Order by Date Filed, rather than by Date Posted.

Nov 6

Filed By: Individual No Affiliation [Katherine & Richard Berry]
Filed Date: 11/6/2014
Accession No: 20141106-5156
Description: Supplemental Information of Richard Eugene Berry under PF14-19.
Information: FILE LIST

Summary: Katherine & Richard Berry express their opposition to the proposed Downeast LNG Export Project.

Top


Nov 7

Filed By: Maine Natural Areas Program
Filed Date: 11/7/2014
Accession No: 20141107-5234
Description: Supplemental Information / Request of Maine Natural Areas Program (MNAP) under PF14-19-000. MNAP comments.
Information: FILE LIST

Summary: Maine Natural Areas Program indicates that their database contains no indication of "rare or unique botanical features" at the proposed terminal site; however, they also indicate that their response "is not a substitute for on-site surveys." They also state, "in the absence of a specific field investigation, the Maine Natural Areas Program cannot provide a definitive statement on the presence or absence of unusual natural features at this site."

Top


Nov 10

Filed By: Save Passamaquoddy Bay
Filed Date: 11/10/2014
Accession No: 20141110-5079
Description: NEPA language translation requirements, comment of Save Passamaquoddy Bay under PF14-19, et al.
Information: FILE LIST

Summary: FERC has failed its National Environmental Policy Act (NEPA) requirement to provide documents translated into the Passamaquoddy language and French language for non-English and English-as-second-language speakers in Maine and New Brunswick. FERC must supply previously-published, and future documents in those languages.

Top


Nov 12

Filed By: Save Passamaquoddy Bay
Filed Date: 11/12/2014
Accession No: 20141112-5093
Description: FERC NOI and Scoping Meeting advertising comment of Save Passamaquoddy Bay under PF14-19.
Information: FILE LIST

Summary: FERC failed to advertise its NOI* and the October 22 Scoping Meeting in any Canadian local newspapers — effectively evading Canadian residents' and news media participation at the meeting.

* NOI — Notice of Intent to publish an Environmental Impact Statement.

Top


Filed By: Downeast Liquefaction, LLC Downeast LNG, Inc. Downeast Pipeline, LLC
Filed Date: 11/12/2014
Accession No: 20141112-5375
Description: Downeast Liquefaction, LLC, et. al. submits its Monthly Pre-Filing Status Report No. 3 for the period of October 11, 2014 ? November 10, 2014, under PF14-19-000.
Information: FILE LIST

Summary: The report includes Downeast LNG activity re Engineering Design; Pipeline (no work reported this month); Environmental; Alternatives Analysis; and other activity. Also reported is Stakeholder Communications and Agency Communications.

Top


Nov 13

Issued By: ENERGY PROJECTS, OFFICE OF [FERC]
Filed Date: 11/4/2014
Accession No: 20141104-4001
Description: Transcript of the 10/22/14 scoping meeting held in Robbinston, ME re Downeast Liquefaction, LLC's project under PF14-19.
Information: FILE LIST

Summary: Scoping Meeting transcript. NOTE: Although the filed date was Nov 4, this filing did not appear on the FERC eLibrary Docket until Nov. 13.

Top


Filed By: INDIVIDUAL [Paul Strickland]
Filed Date: 11/12/2014
Accession No: 201401113-0009
Description: Comments of Paul R. Strickland re the proposed Downeast LNG Export Project under PF14-19.
Information: FILE LIST

Summary: FERC gave inadequate notice of the Scoping Meeting. FERC made intentional errors in the previous Final Environmental Impact Statement. Paul Strickland asks FERC if it intends to correct those errors prior to continuing the permitting process. Since more sound-producing equimpment is now being proposed, are sound barriers being considered? Concerns are expressed regarding storage and use of highly-combustive hydrocarbons required for the liquefaction process. Air pollution from the liquefaction process is expressed as a concern. Negative impacts on local water quality are mentioned. Eminent domain re the proposed pipeline is a concern.

Top


Nov 14

Filed By: Save Passamaquoddy Bay
Filed Date: 11/14/2014
Accession No: 20141114-5202
Description: Contents of Maine Department of Inland Fisheries and Wildlife letter to Downeast LNG, comment of Save Passamaquoddy Bay under PF14-19.
Information: FILE LIST

Summary: Downeast LNG evaded reporting the contents of a letter from the Maine Department of Inland Fisheries and Wildlife (MDIFW) in DeLNG's monthly Pre-Filing Status Report No. 3 posted to the docket on Nov 12. Save Passamaquoddy Bay obtained a copy of the letter, and posted it to the docket here. MDIFW lists numerous environmental concerns in its letter to DeLNG.

Top


Nov 17

Filed By: Individual No Affiliation [Carl & Heather Ross]
Filed Date: 11/17/2014
Accession No: 20141117-5005
Description: Comment of Carl and Heather Ross in Docket(s)/Project(s) PF14-19-000 Submission Date: 11/14/2014
Information: FILE LIST

Summary: The Rosses express their opposition to Downeast LNG, and provide a list of safety, environmental, and esthetic reasons for their opposition.
 
NOTE: This comment actually appeared on the FERC docket on Friday, Nov 14, despite FERC's Accession Number indicating Nov 17.

Top


Filed By: Save Passamaquoddy Bay
Filed Date: 11/17/2014
Accession No: 20141117-5026
Description: FERC NOI and Scoping Meeting proposed project area comment of Save Passamaquoddy Bay under PF14-19.
Information: FILE LIST

Summary: FERC has once again violated the National Environmental Policy Act (NEPA), as well as the public trust. FERC's NOI (Notice of Intent to prepare an Environmental Impact Statement) re the proposed Downeast LNG Export Project, and notice of the FERC Scoping Period, intentionally omits in its project area map the 4,000-foot-long trestle and pier. In doing so, FERC has exhibited its prejudice in favor of the proposed project by "minimizing" the apparent impact, while simultaneously withholding critical information from public stakeholders.

Top


Nov 19

Filed By: Save Passamaquoddy Bay
Filed Date: 11/19/2014
Accession No: 20141119-5044
Description: NEPA and safety regulations scoping comment of Save Passamaquoddy Bay under PF14-19.
Information: FILE LIST

Summary: FERC has violated NEPA (National Environmental Policy Act) throughout Downeast LNG permitting (examples provided). FERC is also ignoring a fatal public safety regulatory issue re vapor fence integrity along the pier trestle.

Top


Filed By: Downeast Liquefaction, LLC Downeast LNG, Inc. Downeast Pipeline, LLC
Filed Date: 11/19/2014
Accession No: 20141119-5140
Description: Downeast Liquefaction, LLC, et. al. updated correspondence under PF14-19.
Information: FILE LIST

Summary: Since FERC has extended the Scoping Period Deadline, Downeast LNG delays filing its Resource Reports until 2015 January.

Top


Nov 24

Issued By: ENERGY PROJECTS, OFFICE OF [FERC]
Filed Date: 11/24/2014
Accession No: 20141124-4008
Description: Bi-Weekly conference call notes, dated 11/10/14 re the Downeast LNG Export Project under PF14-19.
Information: FILE LIST

Summary:

  • Downeast LNG updated Robbinston Planning Board with revised site plan and project description.
  • Initiated and completed onshore geotechnical surveys. Offshore surveys delayed due to weather.
  • Hosted geotechnical review with FERC and FERC’s seismic consultant at project site in Robbinston (added one onshore boring).
  • Initiated and completed marine surveys (lobsters).
  • Eel grass survey completed. Downeast will provide copies to agencies that requested and the
    results will be incorporated into the draft resource reports.
  • Visual resource impact assessment being conducted from water-side. Land side completed.
  • Using historic photos as well for visual impacts.
  • Engineering contractor meetings being initated.
  • Filed DOE application. [This is a required application to export natural gas from the US, and is separate from the FERC application process.]
  • Anticipated filing of draft resource reports week of 11/17/2014. [NOTE: On Nov 19 DeLNG announced it is delaying filing its Draft Resource Reports until 2015 January.]

Top


Nov 26

Filed By: Individual No Affiliation [Jeff Humme & Mary Jane Sylvesterl]
Filed Date: 11/26/2014
Accession No: 20141126-5002
Description: Comment of Jeff D. Hummel in Docket(s)/Project(s) PF14-19. Submission Date: 11/25/2014
Information: FILE LIST

Summary: The commenters list added truck traffic, impacts on local freshwater supply, safety hazards, environmental hazards, and health issues as to why they oppose Downeast LNG.

Top


Add our banner to your webpage: Save Passamaquoddy Bay

Read about the effort to Fix FERC: FixFERC



@MEMBER OF PROJECT HONEY POT