Loading
|
|
"For much of the state of Maine, the environment is the economy" |
Color Key: | Project Developer, Contractors & Supporters Project Opponents Project Neutral Unknown, non-public comments |
2016 | | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
2015 | | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
2014 | | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
2013 | | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
2012 | | Jan | Feb | Mar | Apr | May | Jun | Jul | |
2011 | | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
2010 | | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
2009 | | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
2008 | | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
2007 | | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
Listed here in Ascending Date Order by Posted Date, rather than by Filed Date to FERC eLibrary.
NOTE: The Docket List on the FERC website is in Date Order by Date Filed, rather than by Date Posted.
Aug 2 | Filed By: Individual No Affiliation [RADM Brian Flynn, Assistant Surgeon General (USPHS, retired)] Summary: This is a followup letter from RADM Flynn's May 6 question to the docket. RADM Flynn again asks in what document and at what point FERC determines how Downeast LNG relates to current need and supply. |
Aug 5 | Issued By: ENERGY PROJECTS, OFFICE OF [FERC] Summary: FERC requires Downeast LNG to provide evidence by August 15 that the company has the right to use the proposed terminal property. Downeast LNG's option to purchase the terminal property expired on June 16, so FERC wants to know if the owner granted another option. |
Aug 9 | Filed By: Downeast LNG, Inc. DOWNEAST LNG LP Summary: Downeast LNG reports that the company has bought the Mill Cove property proposed for the terminal. |
Aug 13 | Filed By: DEPARTMENT OF TRANSPORTATION, UNITED STATES [PHMSA] Summary: The US DOT Pipeline and Hazardous Materials Administration (PHMSA) asks for Downeast LNG's recalculated vapor dispersion model results. So far, Downeast LNG has not demonstrated that its vapor dispersion hazard would comply with USDOT Exclusion Zone requirements. |
Aug 30 | Issued By: ENERGY PROJECTS, OFFICE OF [FERC] Summary: FERC communicates to NOAA that Downeast LNG believes it could use vibratory hammering for pile driving, eliminating the need for impact pile driving. That apparently would reduce noise impacts on marine species. FERC also again asks NOAA to agree with FERC's claim that there would be acceptable environmental impacts from the project. Filed By: Save Passamaquoddy Bay Summary: Save Passamaquoddy Bay observes two deficiencies in FERC's 2013 Aug 30 request to NOAA, Accession No. 20130830-3001: |